File #: ID 21-1494    Version: 1 Name:
Type: City Council Item Status: Agenda Ready
File created: 4/12/2021 In control: City Council
On agenda: 4/19/2021 Final action: 4/19/2021
Title: Veterans' Community Park 90% Construction Document Cost Estimate and Project Status
Attachments: 1. Updated 90% Veterans' Community Park Construction Cost Estimate 4-13-21

Agenda Item:  12(c)

Prepared By: Timothy E. Pinter, P.E., Director

Business:   City Council Item

Department:   Public Works Engineering

Subject:

Title

Veterans’ Community Park 90% Construction Document Cost Estimate and Project Status

Body                     

 

 

BACKGROUND:

 

Kimley-Horn and Associates began the design process for Veterans’ Community Park in September 2019 and provided a 60% Design package for review on April 3, 2020.  Subsequent to that project submittal date, on June 5th, 2020, the City of Marco Island hired Manhattan Construction as our Construction Manager at Risk (CMR) for the Park Project.  Today’s item is the submittal and review of the 90% Construction Document Cost Estimate based on the 90% Landscape and Architectural Design plans.

 

Based on the review of the 90% costs, Manhattan will develop the Guaranteed Maximum Price (GMP) for the project and will prepare the GMP Amendment to their service contract with the City. 

 

FUNDING SOURCE / FISCAL IMPACT

 

The current Construction Cost Estimate = $11,054,045.00

 

Manhattan Construction is prepared to provide Value Engineering Cost Options that may reduce the project cost to $9,717,463.00 if accepted by the City Council.

 

The City also received notice that the Florida Recreation Development Assistance Program has awarded a $200,00.00 grant to help pay for the Veterans’ Community Park Play Area.

 

RECOMMENDATION

 

After review of the submittal the staff recommends the City Council review the Value Engineering Options and provide direction for the completion of the GMP for the Park Project.

 

 

POTENTIAL MOTION:  

“I move to accept the Veterans’ Community Park 90% Construction Cost Estimate as submitted by Manhattan Construction on April 13, 2021.”