Agenda Item: 7(j) |
Prepared By: Justin Martin, P.E., Director |
Business: Consent Agenda Item |
Department: Public Works |
Subject:
Title
Authorize the City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., to Excavate 1490 feet of Swale along the Right-of-Way of Lilac Avenue and Apple Court and Replace Two Storm Box Structures at 1211 Lilac Avenue and 800 Apple Court in the Amount of $113,700.00, using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director, Public Works
Body
BACKGROUND: The Swale needs to be Excavated, and the Storm Box Structures need to be Removed and Replaced. The Seawall, Sprinklers, and Driveways will need to be Repaired.
FUNDING SOURCE / FISCAL IMPACT: Funding for this Purchase Order is included in the FY24 Capital Budget “pay as you go” plan under G/L No. 3005410-606300-16027, Citywide Drainage Improvements.
PUBLIC NOTICE REQUIREMENTS: N/A
NOTICE APPEARANCE DATE(S): N/A
RECOMMENDATION: Authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. to Excavate 1490 feet of Swale along the Right-of-Way of Lilac Avenue and Apple Court and Replace Two Storm Box Structures at 1211 Lilac Avenue and 800 Apple Court in the Amount of $113,700.00.
POTENTIAL MOTION: I move to authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. to Excavate 1490 feet of Swale along the Right-of-Way of Lilac Avenue and Apple Court and Replace Two Storm Box Structures at 1211 Lilac Avenue and 800 Apple Court in the Amount of $113,700.00.