Agenda Item: 8(b) |
Prepared By: Justin Martin, P.E., Director, Public Works |
|
Business: Consent Agenda Item |
Department: Public Works |
Subject:
Title
Authorize the City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Installation of a new RCP Pipe at 10 Marco Lake Drive in the Amount of $54,713.80 Using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director of Public Work
Body
BACKGROUND: The Storm Water Pipe needs to be replaced. Old Deltona era corrugated metal pipe which is corroded and is collapsing.
FUNDING SOURCE / FISCAL IMPACT: Funding for this Purchase Order is included in the FY24 Capital Budget “pay as you go” plan under G/L No. 3005410-606300-16027, Citywide Drainage Improvements.
RECOMMENDATION: Authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. for the Installation of a new RCP Pipe at 10 Marco Lake Drive in the Amount of $54,713.80
POTENTIAL MOTION: “I move to authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. for the Installation of a new RCP Pipe at 10 Marco Lake Drive in the Amount of $54,713.80.”