Agenda Item: 7(d) |
Prepared By: Joe Parrilli, Manager |
|
Business: Consent Agenda Item |
Department: Fleet and Facilities |
Subject:
Title
Award of Contract for Kimley-Horn to Provide Construction Documents, Permitting, and Construction Phase Services for the Beach Beautification Project in the Amount of $74,750 - Joe Parrilli, Manager, Fleet & Facilities
Body
BACKGROUND:
The City owns and maintains two public beach access corridors located at S. Collier Blvd and Maple Ave. (435 feet long), and at S. Collier Blvd and Winterberry Drive (530 feet long). Public parking is available near the access points. The proposed project would improve the functionality of these corridors to accommodate the growing use, provide opportunities to educate beachgoers about the unique ecology of southwest Florida shoreline and wildlife, and improve the overall appearance of the access corridors. The project will include bicycle parking, improved landscaping with native plants, lighting for safety that meets sea turtle lighting requirements, educational signs, and public art.
FUNDING SOURCE / FISCAL IMPACT: N / A
The Kimley -Horn proposal will be funded from the previously agreed $257,000 from the City Council, and $147,000 from the TDC. Project total funds of $405,000
PUBLIC NOTICE REQUIREMENTS: N/A
NOTICE APPEARANCE DATE(S): N/A
RECOMMENDATION:
The Kimley -Horn proposal will be funded from the previously agreed $257,000 from the City Council, and $147,000 from the TDC. Project total funds of $405,000
POTENTIAL MOTION:
“I move to authorize the City Manager to accept the Kimley-Horn proposal.”