Title: Authorize the City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement and Storm Sewer Repair at 1423 Jamaica Road in the Amount of $204,600.00 using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director, Public Works
Attachments: 1. Titan Proposal 25091, 2. Titan Contract #2023-029 Fully Executed, 3. Jamaica Road - Titan
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item:  16(a)

Prepared By: Justin Martin, P.E., Director

Business:  City Council Item

Department:  Public Works

Subject:

Title

Authorize the City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement and Storm Sewer Repair at 1423 Jamaica Road in the Amount of $204,600.00 using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director, Public Works

Body                     

 

 

BACKGROUND

 

Inspection of the Stormwater Pipe and Storm Sewer within the easement of 1423 Jamaica Road identified structural deficiencies contributing to repeated washout and ground settlement.  This also includes replacing the cracked sidewalks and driveway, and adding two new storm sewer structures. On December 4, 2023, City Council awarded Contract #2023-029 to Titan Concrete & Utilities, Inc.

 

 

FUNDING SOURCE / FISCAL IMPACT:  Funding for this Purchase Order is included in the FY26 Capital Budget “pay as you go” plan under G/L No. 3005410-606300-16027, Citywide Drainage Improvements.

 

 

PUBLIC NOTICE REQUIREMENTS: N/A

 

 

NOTICE APPEARANCE DATE(S): N/A

 

 

RECOMMENDATION:  Authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement, Storm Sewer Repair, Sidewalk, and Driveway Replacement at 1423 Jamaica Road in the Amount of $204,600.00.

 

 

POTENTIAL MOTION:   I move to authorize the City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement, Storm Sewer Repair, Sidewalk, and Driveway Replacement at 1423 Jamaica Road in the Amount of $204,600.00.