Title: Authorize the Interim City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement at 1455 Collingswood Avenue in the Amount of $68,948.50 using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director, Public Works
Attachments: 1. Titan 68948.50 Estimate, 2. Titan Concrete Contract Fully Executed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item: 7(d)

Prepared By: Justin Martin, P.E., Director Public Works

Business:   Consent Agenda Item

Department:  Public Works

Subject:

Title

Authorize the Interim City Manager to Issue a Purchase Order to Titan Concrete & Utilities, Inc., for the Stormwater Pipe Replacement at 1455 Collingswood Avenue in the Amount of $68,948.50 using the City Public Infrastructure Construction Services Contract 2023-029 - Justin Martin, P.E., Director, Public Works

Body                     

 

 

BACKGROUND:  Inspection of the Stormwater Pipe and Storm Sewer within the easement of 1455 Collingswood Avenue identified structural deficiencies contributing to washout and ground settlement.  This also includes replacing the sidewalks. On December 4, 2023, City Council awarded Contract #2023-029 to Titan Concrete & Utilities, Inc.

 

 

FUNDING SOURCE / FISCAL IMPACT:  Funding for this Purchase Order is included in the FY25 Capital Budget “pay as you go” plan under G/L No. 3005410-606300-16027, Citywide Drainage Improvements.

 

 

PUBLIC NOTICE REQUIREMENTS: N/A

 

 

NOTICE APPEARANCE DATE(S): N/A

 

 

RECOMMENDATION:  Authorize the Interim City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. for the Stormwater Pipe and Sidewalk Replacement at 1455 Collingswood in the Amount of $68,948.50.

 

 

POTENTIAL MOTION:  “I move to authorize the Interim City Manager to issue a Purchase Order to Titan Concrete & Utilities, Inc. for the Stormwater Pipe and Sidewalk Replacement at 1455 Collingswood in the Amount of $68,948.50.”