Title: Authorize the City Manager to Issue a Purchase Order to ADG Architecture, LLC for the Engineering and Architectural Services for the New Public Works Building and Two Outdoor Covered Equipment Storage Pavilions not Exceeding the Amount of $231,068, using City of Marco Island Contract #19-012 - Justin Martin, P.E., Director of Public Works
Attachments: 1. ADG Architecture Proposal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item:  7(c)

Prepared By: Justin Martin, P.E., Director

Business:  Consent Agenda Item

Department:  Public Works

Subject:

Title

Authorize the City Manager to Issue a Purchase Order to ADG Architecture, LLC for the Engineering and Architectural Services for the New Public Works Building and Two Outdoor Covered Equipment Storage Pavilions not Exceeding the Amount of $231,068, using City of Marco Island Contract #19-012 - Justin Martin, P.E., Director of Public Works

Body                     

 

 

BACKGROUND

City staff solicited and received a proposal from ADG Architecture, LLC, an architect contracted under the City’s engineering and architecture professional continuing services contract (19-012), to furnish architectural and related engineering services. The negotiated proposal from ADG is as follows:

 

The project is located at 415 Lily Court, Marco Island, FL, also known as the South Water Treatment Plant., and consists of the design of a new public works building and two outdoor covered equipment storage pavilions. The project is further described as follows:

 

1.                     A new public works facility will be designed.

2.                     Equipment storage pavilions will be designed for the street sweeper, vacuum excavation tuck, traffic signal maintenance truck, excavator, and other heavy equipment and vehicles.

3.                     Work includes adjustments to security gates and fencing, paved parking and design of a new debris staging containment area.

4.                     Geo-technical services will be provided as required for the structure foundations.

5.                     Project will be designed under the new Florida Building and Fire Code, 2023-8th edition.

 

FUNDING SOURCE / FISCAL IMPACT: Included in adopted FY22 and FY24 Capital Budget plans under G/L Nos. 3005410-606200-22016 and 3005410-606200-24002.

 

 

RECOMMENDATION: Authorize the City Manager to Issue a Purchase Order to ADG Architecture, LLC for the new Public Works Building and two Outdoor Covered Equipment Storage Pavilions for the Public Works Department not exceeding the Amount of $231,068.

 

 

POTENTIAL MOTION:  “I move to Authorize the City Manager to Issue a Purchase Order to ADG Architecture, LLC for the new Public Works Building and two Outdoor Covered Equipment Storage Pavilions for the Public Works Department not exceeding the Amount of $231,068.