Legislation Details

File #: ID 25-4303    Version: 1 Name:
Type: City Council Item Status: Agenda Ready
File created: 3/5/2025 In control: City Council
On agenda: 3/17/2025 Final action: 3/17/2025
Title: Change Order for Ajax Paving Inc. in the Amount of $26,456.90, for the Leigh Plummer Parking Lot Repair, to Original Purchase Order #00250384 $49,969.89, bringing Project Price to $76,426.79 - Joe Parrilli, Manager, Fleet & Facilities
Attachments: 1. Leigh Plummer Park Marco Bid Form (002) Original Proposal, 2. Leigh Plummer Park Marco Bid Form Change Order, 3. Leigh Plummer Park ROW Change Order

Agenda Item:  7(d)

Prepared By: Joe Parrilli, Manager

Business: Consent Agenda Item 

Department:  Fleet and Facilities  

Subject:

Title

Change Order for Ajax Paving Inc. in the Amount of $26,456.90, for the Leigh Plummer Parking Lot Repair, to Original Purchase Order #00250384 $49,969.89, bringing Project Price to $76,426.79 - Joe Parrilli, Manager, Fleet & Facilities

Body                     

 

 

BACKGROUND: 

 

The City of Marco Island owns and maintains Leigh Plummer Park. The parking lot at the park is currently undergoing a full replacement due to significant damage that rendered the existing lot beyond the point of resurfacing. Purchase Order #00250384, in the amount of $49,969.89, was issued to Ajax Paving Inc. under Contract 2023-029 for the replacement of the damaged parking lot.

During the course of the project, it was determined that the drive within the right-of-way must be upgraded to comply with current city code requirements. As a result, an additional $26,456.90 is required to complete the necessary upgrades, which include, but are not limited to, new drainage systems, walkways, and grading improvements to meet city standards.

The total project cost is now $76,426.79, and appropriate funding is available in the FY25 budget.

 

FUNDING SOURCE / FISCAL IMPACT: 

 

The original PO#00250384 was funded from parks capital 3005720-606300-24050 in the amount of $49,969.89 and the $26,456.90 change order will come out of the same account, designed for Leigh Plummer parking lot.

 

 

RECOMMENDATION:

 

Staff recommend funding the change order to Ajax Paving Inc for $26,456.90.

 