Legislation Details

File #:    Version: 1 Name:
Type: City Council Item Status: Agenda Ready
File created: 3/4/2025 In control: City Council
On agenda: 3/17/2025 Final action:
Title: Resolution - Approving a Local Agency Program (LAP) Supplemental Agreement with the Florida Department of Transportation (FDOT) for the Construction of the Collier Boulevard Alternate Bike Lanes Project - Justin Martin, P.E., Director, Public Works
Attachments: 1. Resolution 25-20, 2. FDOT Executed LAP Agreement, 3. Local Agency Program Supplemental Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item: 12(a)
Prepared By: Justin Martin, P.E., Director
Business: Resolution
Department: Public Works
Subject:
Title
Resolution - Approving a Local Agency Program (LAP) Supplemental Agreement with the Florida Department of Transportation (FDOT) for the Construction of the Collier Boulevard Alternate Bike Lanes Project - Justin Martin, P.E., Director, Public Works
Body


BACKGROUND:

The attached Resolution will authorize the City Manager to execute a Local Agency Program (LAP) Supplemental Agreement with the Florida Department of Transportation (FDOT) to increase the funding for the construction of the Collier Boulevard Alternate Bike Lanes Project.

The Project will provide in-road bike lanes as an alternate route for bicycle traffic currently traveling either north or south along Collier Boulevard, which is the most heavily traveled roadway on Marco Island and does not have sufficient roadway width to accommodate bicycle traffic or bicycle lanes. The Project will connect to the bike lanes previously installed on Landmark Street and will also provide important linkages to the two major east/west bike lanes currently on San Marco Road and Winterberry Drive, and to the Florida Sun Trail Pathway.

The supplemental agreement increases the FDOT grant funding to $4,279,099. The project will be publicly bid upon execution of the supplemental agreement and approval by FDOT.


FUNDING SOURCE / FISCAL IMPACT: 100% of the project construction costs will be reimbursed by the FDOT grant as outlined in the supplemental agreement. Funds for the project will be added from the city's capital reserves to the existing funds contained within the FY25 Capital Budget account number 300-5400-5410-606300-24006 until replenished by the reimbursement.


RECOMMENDATION: Staff recommends the adoption of Resolution 25-20 and authorization for the City Manager to execute the Collier Boulevard Alternate Bike Lanes Project Local Agency Program (LAP) Supplemental Agreement wit...