Agenda Item: 9(d) |
Prepared By: Jeffrey Poteet, General Manager |
|
Business: Consent Agenda Item |
Department: Water & Sewer Department |
Subject:
Title
Authorize the City Manager to Execute a Change Order to Quality Enterprises USA Inc. for the Replacement of a 20-inch Pipe and Valves at the Reclaimed Water Production Facility, Currently under Contract, in the Amount of $52,400.00. - Jeffrey Poteet, General Manager, Water & Sewer Department
Body
BACKGROUND:
On November 6, 2023, the City of Marco Island approved a purchase order to QE for the replacement of a 20-inch pipe and valves between the influent storage tanks No. 2 and No. 3, located at the Reclaimed Water Production Facility, in the amount of $49,900.
During the initial excavation, it was discovered that the pipe to be replaced was encased in concrete. As a result, the contractor required additional material and time to proceed with the work, as well as the isolation of influent storage tanks 2 and 3. Due to the proximity to the high season and hurricane season, this work was postponed until December 2024. The change order amount is $2,500 to cover the additional mobilization fee.
|
Current Contract Amount |
$49,900.00 |
|
Additional Mobilization Fee (CO-01) |
$ 2,500.00 |
|
Change Order Amount Total |
$52,400.00 |
FUNDING SOURCE / FISCAL IMPACT: Funding for this Change Order is included in the FY25 Capital Improvement Program (4305356-606400-21017)
PUBLIC NOTICE REQUIREMENTS: N/A
NOTICE APPEARANCE DATE(S): N/A
RECOMMENDATION: Authorize the City Manager to Execute a Change Order to Quality Enterprises USA Inc., for the replacement of a 20-inch pipe and valves at the Reclaimed Water Production Facility in the amount of $52,400.00.
POTENTIAL MOTION: “I move to authorize the City Manager to Execute a Change Order to Quality Enterprises USA Inc., for the replacement of a 20-inch pipe and valves at the Reclaimed Water Production in the amount of $52,400.00.”